The hoists are located in the following facilities, building numbers 01, 02, 07, T-09, 14, 91, 139, 140, 152, 153, 159, 176, 200, 709, 1117, 1118, 1119, 1125, 1141, 4047, 4050, 4055, 4077, 5010, 5034 – 5046, 5048 and 5400.

The contractor must be certified and must provide proof in writing that they are experienced in providing maintenance to hoists with nuclear capability.

All inspection and testing procedures shall be in accordance with Air Force Instruction (AFI) 91-46 dated 1 August 02 & MFR.

All hoists in buildings 2, 14, 1141, 4047 and 4055 shall be inspected on a bi-annual basis. Weight tests shall be performed in the month of January. Inspections shall occur in the moths of January and July. All remaining hoists shall be inspected on an annual basis and be performed in January.

Deadline: August 4 2008.

Solicitation number: FA4625-08-Q-0023.